Pembangunan Tanggul A NCICD Muara Baru Sudah 55 Persen
.
photo istimewa - Beritajakarta.id

NCICD Embankment A Project Has Reached 55 Percent

The construction of the National Capital Integrated Coastal Development (NCICD) Embankment A in Muara Baru by Public Works and Public Housing Ministry has touched 55 percent.

It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018

Ferdinanto, Committing Officer for National Higher Education Fund Corporation (PTPIN) said the embankment project is in accordance with Presidential Regulation No. 58/2017 about acceleration of national strategic projects.

"It will be accelerated and is targeted to be completed in the forthcoming December, from the initial plan in early April 2018," he stated, Wednesday (7/26).

Acting Governor to Visit NCICD Phase A Construction

The construction process on the second phase of the first package embankment (Muara Baru-Pluit) as long as 1.2 kilometers is accelerated. Hopefully, it could be completed as expected.

"No delay. The construction has reached 55 percent so far," he closed.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1519 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye941 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye449 personBudhi Firmansyah Surapati
  4. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye423 personDessy Suciati
  5. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye412 personFolmer